How to quote a renovation from the drawings
A new build is measured. A renovation is measured and then argued with: what's new, what's existing, what's behind the plaster. The quote that survives is the one that says which is which.
Tell new from existing
Architects show it by convention: existing walls solid or grey, new walls hatched or heavier, demolished walls dashed, and a demolition plan on a bigger job. Read the legend before you measure anything. Where the drawings don't make it clear, list the question rather than decide it for them.
Measure the new work only
Walls, rooms, openings, linings, finishes and roof for the new work, exactly as you'd take off a new build. Then the junctions: where new meets existing there's patching, matching, a new skirting against an old one, a roof tie-in with a valley and a flashing. These are lines of their own, and they're where renovation money goes.
Price the demolition and the unknowns
- Demolition as lines: walls removed (lm or m2), fittings removed, rubbish (m3 or loads), making good
- Provisional sums for work you can't see: the termite damage, the slab under the old kitchen, the electrical that isn't to code
- An asbestos allowance on anything pre-1990, with the inspection as the first line
- Access and protection: floor protection, dust walls, the client living there
Where the software comes in
Plyrow reads which walls are new and which are existing from the drawing's own conventions, measures the new work, lists demolition where the plans show it, and puts whatever the drawings don't settle in Check these as a question for you or the client, never as a number in the quote.
Fixed price for the drawn work with provisional sums for the unknowns is what most clients will sign. Cost plus suits a job where nobody knows the scope yet, and needs a client who trusts you.
Enough that you don't lose on the first surprise: 10 percent of the renovation cost is common on older houses, named as a provisional sum so the client sees it and gets back what isn't used.
- How to measure plasterboard off the plans
- Quote or estimate? What each one commits you to
- How to read a door and window schedule
- Margin vs markup: the arithmetic that decides your profit
- How to measure brick veneer from the elevations
- How to measure a roof from the plans
- What a bill of quantities for a house should include
Bring one process. We'll show you what fits.
We're in Brisbane, and on calls across Australia and the US.
Book a 30-minute call
Tell us about the process that eats the week. No cost, no obligation.
Book a call louis@plyrow.com +61 455 504 104Brisbane, Australia