What a bill of quantities for a house should include

A BOQ is complete when every trade that will send an invoice has lines on it. Here are the trades in build order, what each measures, and the lines that are forgotten most.

Before the slab

  • Preliminaries: site establishment, fencing, toilet, power and water, insurance, supervision, scaffold
  • Site works: cut and fill (m3), retaining (m2 or lm), stormwater and sewer (lm), driveway and paths (m2)
  • Demolition on a renovation, as its own lines

Structure

  • Slab and footings: concrete (m3), reinforcement, formwork, vapour barrier, termite treatment
  • Framing: wall framing by type and height (lm or m2), plates, lintels, roof framing or trusses, bracing, tie-downs
  • Masonry: veneer or double brick (m2), lintels (each), piers, sills, ties

Envelope

  • Roof: covering on the slope (m2), ridge, hip, valley, gutter, fascia (lm), downpipes (each), sarking, insulation
  • Windows and doors, each by tag, with hardware
  • Cladding (m2), wrap, flashings and trims (lm), eaves linings

Fit-out and finishes

  • Linings and cornice; skirting and architrave; internal doors with hardware
  • Waterproofing, tiling (floor and wall, m2), painting (m2 and each), floor coverings
  • Kitchen, bathroom and laundry joinery; benchtops; appliances as prime cost items
  • Electrical and plumbing, usually as subcontract sums with the fixtures listed

The ones that get left off

Scaffold on a two-storey; the second top plate on load-bearing walls; the wet-area board; waterproofing as its own certificate; the meter box and the temporary power; the driveway crossover the council insists on; cleaning; the margin on the prime cost items. Each one is a line someone will invoice.

Plyrow's BOQ starts from the drawings with every residential trade in this order, and its AI reader lists what no line covers before the quote goes out.

FAQ

Questions, answered.

Anything else, ask us on a call.

Get in touch

Many builders attach a summary by trade and keep the line detail. A client who can see how the price was built argues less about it.

A BOQ has quantities and prices; a schedule of rates has prices per unit and the quantities are measured as built. Houses are quoted on a BOQ; the schedule of rates covers variations.

Reach out

Bring one process. We'll show you what fits.

We're in Brisbane, and on calls across Australia and the US.

Book a 30-minute call

Tell us about the process that eats the week. No cost, no obligation.

Book a call louis@plyrow.com +61 455 504 104

Brisbane, Australia